Top Project Risk Number 3: Scope Risk

Will I get everything I asked for?

Imagine it is Saturday, your spouse is about to go out somewhere with the car, and you need groceries. You ask him or her to stop at the grocery store on the way home. “Of course, send me the list!” You text the list of groceries for the week and then add, “For our guests tonight we need meat, wine, and cheese.” Your spouse returns at six that evening with everything but the meat, wine, and cheese. “How could you not bring tonight's dinner!?” “Oh, that was at the bottom of the list and I was running late, so I didn't get to it.”
Obviously, getting everything would have been the best solution, but if you had to choose between ‘things for next week’ and ‘things for tonight’, which is more important? Which alternative gives you better options?

Time, budget and scope are the classic measures of success of a project. Is it on time and on budget? Did it deliver all the features? Of these three, scope is probably the least important. Being on time with the most important features is usually better than being late with all the features.

Scope risk mitigation in Scrum 

The underlying challenge is that we have more good ideas than time and resources to implement them. Which of these are really essential? And which could you live without?

Scrum ensures that you deliver the most important features first by slicing features into small chunks, prioritizing them, and only working on a small number of high priority features at a time. Collaboration with the client side is essential to get the sequencing right. If you are going to fail to deliver something, skip a nice-to-have, not a must-have.

Scrum is not designed to deliver the exact contents of a shopping list. As a client, you can constrain Scrum with some kind of Fixed Scope contract, but it is probably not in your interest to do so. The vendor will need to add buffers to accommodate the risks. You will need a change management process to manage the inevitable change requests. That change management process itself costs time and money and its true purpose is to raise the cost ceiling. Selecting the vendor through a competitive bidding process incentivizes the vendors to bid low, skimp on quality, and earn their money back through the change request process and maintenance.

Comments

Popular posts from this blog

Sample Definition of Done

Why does Scrum have a Definition of Done? Simple, everyone involved in the project needs to know and understand what Done means. Furthermore, Done should be really done, as in, 'there is nothing stopping us from earning value with this function, except maybe the go-ahead from the Product Owner. Consider the alternative:
Project Manager: Is this function done?
Developer: Yes
Project Manager: So we can ship it?
Developer: Well, No. It needs to be tested, and I need to write some documentation, but the code works, really. I tested it... (pause) ...on my machine. What's wrong with this exchange? To the developer and to the project manager, "done" means something rather different. To the developer in this case, done means: "I don't have to work on this piece of code any more (unless the tester tells me something is wrong)." The project leader is looking for a statement that the code is ready to ship.

At its most basic level, a definition of Done creates a sh…

Explaining Story Points to Management

During the February Scrum Breakfast in Zurich, the question arised, "How do I explain Story Points to Management?" A good question, and in all honesty, developers can be an even more critical audience than managers.

Traditional estimates attempt to answer the question, "how long will it take to develop X?" I could ask you a similar question, "How long does it take to get the nearest train station?

The answer, measured in time, depends on two things, the distance and the speed. Depending on whether I plan to go by car, by foot, by bicycle or (my personal favorite for short distances) trottinette, the answer can vary dramatically. So it is with software development. The productivity of a developer can vary dramatically, both as a function of innate ability and whether the task at hand plays to his strong points, so the time to produce a piece of software can vary dramatically. But the complexity of the problem doesn't depend on the person solving it, just …

Money for Nothing, Changes for Free

“Money for Nothing, Changes for Free” encourages both customers and suppliers to focus on value.

A key advantage of Scrum projects is that at least once per sprint you have something that could be shipped and no work in progress. You can change direction every sprint, and you can reevaluate whether the project is a good investment or if your money could be better spent elsewhere. Abrupt cancellation is risky for the supplier.

While the concept of an early-exit penalty is not new, Jeff Sutherland gave it a unique allure with his allusion to the Dire Straits hit.
Desired Benefit Incentivize both customers and suppliers to focus on functionality that provides genuine value.
Structure This works with Agile software projects because there is little or no work in progress. After each Sprint, functionality is either complete or not started. Work is basically on a Time and Materials basis with a cost target, often with the intention that the project should not use up the entire project budge…