How to evaluate a contract for your Agile project

Commercial contracts can take many forms. What are the contract alternatives that are suitable for agile development projects?

Beware of traps in contracts you didn't write.
Gopher Traps courtesy of  El Cajon Yacht Club


For any contract, I would look at:
  • What are the intended benefits?
  • How is the contract structured? What are the basic rules for delivering scope and invoicing revenue?
  • How does it apportion Risk and Reward between customer and supplier? 
  • How does it handle decision making and changes in requirements? 
  • What model of customer relationship does it foster: competitive (my win is your loss), cooperative (win-win), indifferent (I don’t care-you lose) or dependent (heads-I-win-tails-you lose)? 
If I did not draft the contract, I would also look for traps - contract negotiation can be a competitive game. One place to look for traps is language that you do not understand. Another place is references to laws that you may not be familiar with. The question is what do you do if you find a trap? Try to get it taken out, or accept it and move on? Let's just call this a 'business decision'.



The text is excerpted from Ten Contracts For Your Next Agile Project, by Peter Stevens. 
You can get the whole book now, or you can read it a chapter at a time as I publish it here under the label ten contracts. To download the e-book or pre-order the physical book visit https://saat-network.ch/ten

EDIT: 190602 added picture

Comments

Popular posts from this blog

Sample Definition of Done

Why does Scrum have a Definition of Done? Simple, everyone involved in the project needs to know and understand what Done means. Furthermore, Done should be really done, as in, 'there is nothing stopping us from earning value with this function, except maybe the go-ahead from the Product Owner. Consider the alternative:
Project Manager: Is this function done?
Developer: Yes
Project Manager: So we can ship it?
Developer: Well, No. It needs to be tested, and I need to write some documentation, but the code works, really. I tested it... (pause) ...on my machine. What's wrong with this exchange? To the developer and to the project manager, "done" means something rather different. To the developer in this case, done means: "I don't have to work on this piece of code any more (unless the tester tells me something is wrong)." The project leader is looking for a statement that the code is ready to ship.

At its most basic level, a definition of Done creates a sh…

Explaining Story Points to Management

During the February Scrum Breakfast in Zurich, the question arised, "How do I explain Story Points to Management?" A good question, and in all honesty, developers can be an even more critical audience than managers.

Traditional estimates attempt to answer the question, "how long will it take to develop X?" I could ask you a similar question, "How long does it take to get the nearest train station?

The answer, measured in time, depends on two things, the distance and the speed. Depending on whether I plan to go by car, by foot, by bicycle or (my personal favorite for short distances) trottinette, the answer can vary dramatically. So it is with software development. The productivity of a developer can vary dramatically, both as a function of innate ability and whether the task at hand plays to his strong points, so the time to produce a piece of software can vary dramatically. But the complexity of the problem doesn't depend on the person solving it, just …

Money for Nothing, Changes for Free

“Money for Nothing, Changes for Free” encourages both customers and suppliers to focus on value.

A key advantage of Scrum projects is that at least once per sprint you have something that could be shipped and no work in progress. You can change direction every sprint, and you can reevaluate whether the project is a good investment or if your money could be better spent elsewhere. Abrupt cancellation is risky for the supplier.

While the concept of an early-exit penalty is not new, Jeff Sutherland gave it a unique allure with his allusion to the Dire Straits hit.
Desired Benefit Incentivize both customers and suppliers to focus on functionality that provides genuine value.
Structure This works with Agile software projects because there is little or no work in progress. After each Sprint, functionality is either complete or not started. Work is basically on a Time and Materials basis with a cost target, often with the intention that the project should not use up the entire project budge…