WTO Bidding Process Considered Harmful

I've long believed that the WTO bidding process for IT projects is an expensive, wasteful process. By its very nature, it forces a waterfall process, which the CHAOS and other studies (despite their shortcomings) have shown produce a consistent 60 to 70% failure rate.

Of course it is mandated by law, so everyone has no choice but to play along. But at what cost? Finally, this issue is getting some attention. Today, ComputerWorld.ch documented the many shortcomings of the WTO Process (here is a translation from Google):
  1. The losers invest at least as much effort in bidding for the project as the project is worth. WTO projects are a net loss for the economy.
  2. Companies involved in preparing the RFP are not allowed to bid - all the context information is lost, so quality is lowered and the costs increase.
  3. Government agencies can and do write the RFP so that only one supplier actually has a real chance of winning the project.
  4. The process is vulnerable to price-dumping which a low price dominates other considerations (e.g. quality).
To this discussion, I would add: the WTO Process values features over business value.

 In the Spring of 2008, I led a proposal effort in response to an RFP from a Swiss Government Agency (who shall remain nameless). The Christmas season was very important to the revenue of this agency. Our proposal offered the advantage that they would have a working (though incomplete) system in time for Christmas of 2008 instead of 2009 which would let them generate ROI a year earlier. The response: "Our decision criteria do not require operation this year, so your advantage, while interesting, is not something which can affect our decision." AFAIK, their 'Hoflieferant' (established supplier) got the contract.

Is there a better way? Yes I think so. I have written about how an agile bidding process might work. What we need is an agency who wants to look for a better way. We could define and try out an agile bidding process. Any one interested? Drop me a line...







Comments

Popular posts from this blog

Sample Definition of Done

Why does Scrum have a Definition of Done? Simple, everyone involved in the project needs to know and understand what Done means. Furthermore, Done should be really done, as in, 'there is nothing stopping us from earning value with this function, except maybe the go-ahead from the Product Owner. Consider the alternative:
Project Manager: Is this function done?
Developer: Yes
Project Manager: So we can ship it?
Developer: Well, No. It needs to be tested, and I need to write some documentation, but the code works, really. I tested it... (pause) ...on my machine. What's wrong with this exchange? To the developer and to the project manager, "done" means something rather different. To the developer in this case, done means: "I don't have to work on this piece of code any more (unless the tester tells me something is wrong)." The project leader is looking for a statement that the code is ready to ship.

At its most basic level, a definition of Done creates a sh…

Scaling Scrum: SAFe, DAD, or LeSS?

Participants in last week's Scrum MasterClass wanted to evaluate approaches to scaling Scrum and Agile for their large enterprise. So I set out to review the available frameworks. Which one is best for your situation?

Recently a number of approaches have started gaining attention, including the Scaled Agile Framework ("SAFe") by Dean Leffingwell, Disciplined Agile Development (DAD), by Scott Ambler, and Large Scale Scrum (LeSS), by Craig Larman and Bas Vodde. (Follow the links for white papers or overviews of each approach).

How to compare these approaches? My starting point is Scrum in the team. Scrum has proven very effective at helping teams perform, even though it does not directly address the issues surrounding larger organizations and teams. An approach to scaling Scrum should not be inconsistent with Scrum itself.

Scrum implements a small number of principles and constraints: Inspect and Adapt. An interdisciplinary Team solves the problem. Deliver something of va…

What is the role of a Business Analyst in Scrum?

When I teach a CSM class, my goal is that my participants go home delighted (and of course that they learn about Scrum, that they are motivated to do Scrum, and can pass the online CSM exam). So after every class, I ask for feedback, in particular what could I do to get a better score. And for the next class, I strive to implement or address two or three of the points raised by my participants.

One issue that was raised was unanswered questions. It is annoying to ask questions and not get answers! Time is limited, so it is not always possible to answer all questions, so I thought, why not answer them on my blog? So here goes, first question:
What is the role of a Business Analyst in Scrum? This question is a challenge because Scrum doesn't answer this question! Scrum is a simple, team-based framework for solving complex problems. The roles and ceremonies in Scrum are designed to ensure that inspect and adapt can occur regularly with complete and correct information. Scrum does not…